Friday, February 10, 2012

South Exterior Wall PLASTERED




Yay Team! Just a quick six days and poof, plastered wall.

Day 1 Prep: 5 hours Alaine
Day 2: 2.5 hours Aliane
Day 3: 7.5 + 3 hours Noble
Day 4: 8.5 + 4 hours Noble
Day 5: (today) 7 hours + 5 hours Noble
Day 6: 8.5 + 2 hours Noble
Total: 60 hours!

Thursday, February 9, 2012

Thirty Some Feet in the Air!

 I got the middle section, arched part, plastered, didn't get the in-between picture though.
Spent 8.5 hours doing that.
Then, a calm windless day, we hooked up a saftey built and Noble belayed me. We were really high tech. He looked up how to wrap a big rope rope around me (not so comfy) and then found a carabiner and hooked it to a long extension cord.
Luckily, no problems. and LUCKLY after just 7 hours, got that hard part done!
Day 1 Prep: 5 hours Alaine
Day 2:  2.5 hours Alaine
Day 3:  7.5 + 3 hours Noble
Day 4:  8.5 + 4 hours Noble
Subtotal: 30.5 hours so far


Can we get it done in one more day?



Tuesday, February 7, 2012

2nd Day Plastering the Exterior South Wall



Gotta make sure it's not a windy day when one is plastering twenty some feet in the air on a not-very-stable platform.
Day 1: 5 hours Alaine prep

Day 2: 2.5 hours Alaine

Day 3: 7.5 + 3 hours Noble

Subtotal: 18 hours.

Any other guesses for total hours to plaster this whole side?